Court Insights | ADGM Courts & Construction Contracts | 23 November 2026
A subcontract can say that the main contractor chooses the sole arbitrator without giving it the final say. The question for a tender team is whether that promise fits the rules it incorporates in the very same sentence. An ADGM construction judgment shows what happens when those instructions point in different directions (ADGM Court of First Instance, [2026] ADGMCFI 0012, paragraphs 2 and 52–68).
One clause, two appointment mechanisms
The subcontract chose an ADGM seat, English-language arbitration and administration by the International Chamber of Commerce (ICC). It also said that the sole arbitrator would be appointed by the main contractor. The ICC Court appointed the arbitrator instead; the main contractor challenged the appointment (ADGM judgment, paragraphs 2 and 15–20).
The judge upheld the appointment. Under the rules incorporated into this subcontract, the parties’ chosen method was subject to the ICC Court’s exceptional appointment power. The judge did not declare every unilateral appointment clause invalid or make a fresh finding that the circumstances were exceptional. The decision turned on what the parties had agreed the institution could decide, and which decisions were final under its rules (ADGM judgment, paragraphs 52–58 and 62–70, discussing sections 19–21 of the ADGM Arbitration Regulations 2015).
What to change before issuing the subcontract
Ask the project director why the business wants to choose the arbitrator. If the answer is “we need someone who understands delay analysis and complex variations”, solve that problem directly. Specify the expertise that matters, give both sides a defined opportunity to nominate a suitable person, and provide for institutional appointment if they cannot agree. Avoid requirements so narrow that only one person could qualify.
Now compare the main contract, subcontract conditions and tender amendments. If one says the contractor “appoints” and another says it “nominates for confirmation”, decide which power is intended. State who acts if a nominee declines or discloses a conflict. Test the clause from the subcontractor’s seat too: could it tell, without a side agreement, how a sole arbitrator would be selected if the relationship had already broken down?
For new drafting, use the right edition. The judgment considered Article 12(9) of the earlier ICC Rules; the 2026 Rules generally apply to arbitrations commenced from 1 June 2026 unless the parties agreed on an earlier edition. The corresponding exceptional appointment power is now Article 13(10) (ICC Arbitration Rules 2026, Articles 1(2) and 13(10)).